Patriot Renewables, LLC, the renewable energy affiliate of Jay Cashman, Inc., is studying the feasibility of siting an offshore wind farm project in Buzzards Bay.
South Coast Wind is committed to working cooperatively with local communities and organizations to develop a viable wind energy project that will meet the energy needs of the region and bring new jobs, vitality and tourism to the area.
• 150 MW to 200 MW Total
• 40 to 60 turbines overall
• 3.0 MW to 5.0 MW per turbine
• Turbines will be spaced approximately ¼ to ½ miles apart
• Final turbine locations will depend on turbine selection, environmental factors and wind regime
Manufacturer |
Size |
Hub
Height |
Rotor
Diameter |
Blade
Length |
Max. Height of
Blade Tip |
Min. Height of
Blade Tip |
Siemens |
3.6 MW |
262 feet
(80 meters) |
351 feet
(107 meters) |
171 feet
(52 meters) |
438 feet
(133.5 meters) |
87 feet
(26.5 meters) |
Vestas |
3.0 MW |
262 feet
(80 meters) |
295 feet
(90 meters) |
144 feet
(44 meters) |
410 feet
(125 meters) |
115 feet
(35 meters) |
REpower |
5.0 MW |
295 feet
(90 meters) |
413 feet
(126 meters) |
202 feet
(61.5 meters) |
502 feet
(153 meters) |
89 feet
(27 meters) |
|